Smith High School (Other Funding Sources)

This project is paid for with 2003 Bond Funds.

Renovations at Smith High School will focus primarily on enhancing the exterior front entrance.

Improvements

  • Exterior improvements – COMPLETED
    • New canopy at the main entrance- COMPLETED
    • New screen walls and canopies at the secondary entrances- COMPLETED
    • New landscaping along the façade- COMPLETED
    • New monument sign- COMPLETED

Current Status:

Construction contract was awarded to W. B. Kibler Construction at April 2019 board meeting. Construction began in June 2019.

As of October 2019, the new canopy at the main entrance and monument sign are complete.  The new screen walls and canopies at the secondary entrances are complete.